CoreSite SV-6 Data Center

Project Details

0
square feet
0
days to erect
Location: Santa Clara, CA
Owner: CoreSite
GC: MATT Construction
Engineer: FBA Engineers
Architect: DCM

Project Narrative

This 136,000 ft2 data center was erected in just 9 days. SV-6 is the third CoreSite data center with a ConXL structural frame on CoreSite’s Silicon Valley campus.

ConX Solutions

The ConXL System addressed CoreSite’s need for a robust, long-span steel data center frame delivered cost-effectively and with increased speed to market. ConXL’s inherent lack of shear walls and bracing allow for a fully open and reconfigurable floor plan which provides ultimate flexibility for mechanical system routing and future upgrades. The ConXL System also delivered a solution for the highly concentrated floor loadings (275 psf) required with unparalleled structural efficiency.

Download Project Bio

This project has a ConXL 400 chassis:

Lower & Locking™ Connection

ConXL 400

Height & Assembly Speed

  • 2 to 10 Stories

  • 10 to 15,000 ft2 per day

Design Parameters

Column Size 400 mm (16″ HSS or Box)
Beam Depth 18″ to 30″ for SMF, deeper for OMF
Beam Spans 18′ to 45’+