COURTYARD MARRIOTT MONTEREY PARK

Project Details

0
square feet
0
days to erect
Location: Los Angeles, CA
Owner: Ethan Capital LLC
GC: KCS West
Engineer: Saiful Bouquet Structural Engineers
Architect: Gene Fong Associate

Project Narrative

This six-story, 210,000 ft² hotel features 288 guest rooms, a second floor pool deck, ground floor retail space, and two levels of subterranean parking. The structural steel portion of the construction was assemled in only eight days, with more than 120 pieces of steel being erected per day. It’s also located directly across from Monterey Park’s bustling Atlantic Times Square, a 200,000+ft2 mixed-use development featuring hotels and commercial/retail space.

This project has a ConXR™ 200 chassis:

Lower & Locking™ Connection

ConXR 200 System Connection
ConXR 200

Height & Assembly Speed

  • 4 to 8 Stories, up to 12

  • 3 to 5,000 ft2 per day

Design Parameters

Column Size 200 mm (8″ HSS)
Beam Depth 12″ (variable weight)
Beam Spans 8′ to 20′