SANTA MONICA HIGH SCHOOL DISCOVERY
BUILDING Education
Project Data
0
square feet
0
days to erect
Number of Collars | Bay Spacing | Structure Weight |
---|---|---|
153 | 38’-0” | 1360 tons |
Location: | Santa Monica, CA |
---|---|
Owner: | Santa Monica -Malibu Unified School District |
GC: | McCarthy Construction |
Engineer: | Saiful. Bouquet Structural Engineers |
Architect: | HED Design |
Steel Fabricator: | ConXtech/Zamil |
Steel Erector: | ConXtech |
ConXtech Scope: | Main Structural Steel |
Project Narrative
The Santa Monica High School Discovery Building is a new 3-story structure erected on top of podium level parking. This innovative building was designed using the “open building” design concept, with a flexible, open-column grid, raised floors and non-load bearing walls which can be reconfigured over time. ConXtech’s brace-free structural solution was an integral part of making that possible. The project has been recognized as the winner of the ENR California Best Projects 2022: Best K-12 Education, among various other recognitions.
This project has a ConXL 400 chassis:
Lower & Locking™ Connection
Height & Assembly Speed
Design Parameters
Column Size | 400 mm (16″ HSS or Box) |
Beam Depth | 18″ to 30″ for SMF, deeper for OMF |
Beam Spans | 18′ to 45’+ |